The project manager for a construction project discovers that a new water line is being created in the neighborhood where he’s managing a project. Company policy requires that a series of forms for city environmental changes need to be filled out before his team can continue work on the project. This is an example of:
a portfolio

a program

an enterprise environmental factor

a project

Fenster schliessen
Which of the following is NOT a characteristic of a project?
temporary

strategic

specific result

progressively elaborated

Fenster schliessen
An energy company is investing in a series of initiatives to look for alternative energy sources so that the company can be competitive in 10 years. The initaitives are tracked and managed together because this goal is vital to the success of the company. This is an example of...
a portfolio

a program

a project

an enterprise environmental factor

Fenster schliessen
Which of the following is NOT a responsibility of a project manager?
managing stakeholder expectations

managing project constraints

gathering product requirements

sponsoring the project

Fenster schliessen
Which of the following is NOT a Process Group?
Monithoring an Controlling

Gathering Requirements

Initiating

Closing

Fenster schliessen
Which of the following is NOT a knowledge area?
Scope

Integration

Procurement

Initiating

Fenster schliessen
Which of the following is NOT true about portfolio management?
The portfolio manager judges success of the portfolio by combining data from all of its programs and projects

A portfolio can contain projects and programs

A portfolio is organized around a business goal

A portfolio is always a group of programs

Fenster schliessen
You’re managing a project to remodel a kitchen. You use earned value calculations to figure out that you’re going to run $500 over budget if your project continues at the current rate. Which of the following core characteristics of a project manager are you using to find the problem?
Knowledge

Performance

Personal

None of the above