The person who should be in control of the project during project planning is the:

Team member

Sponsor

Project manager

Functional manager

Fenster schliessen

Which of the following is a characteristic for projects?

Standardized

Iterative

Unnecessary

Unique

Fenster schliessen

PMI standard consists of

1 project charter, 1 management plan, 1 integrated change controll

4 phases, 10 templates, 12 milestones

5 Knowledge areas, 10 process groups, 74 processes

10 Knowledge areas, 5 process groups and 47 processes

Fenster schliessen

Which of the following are inputs to the process 'Identify stakeholders?

Enterprise environmental factors, procurement documents, project charter, network diagram

Organizational process assests, risk register, procurement documents, project charter

Organizational process assests, enterprise environmental factors, stakeholder register, project charter

Organizational process assests, enterprise environmental factors, procurement documents, project charter

Fenster schliessen

Which of the following is included in a project charter?

A risk management strategy

The business need for the project

Work package estimates

Detailed resource estimates

Fenster schliessen

The high-level project schedule constraints have just been determined. Which
project management process group are you in?

Initiating

Planning

Monitoring and Controlling

Executing

Fenster schliessen

Which of the following characteristics describe a program?

Costs: medium, duration: medium-/large, importance: medium-high

frequency: uniquely, duration: medium-/large, importance: medium-high

Costs: high, duration: medium-/long-term, frequency: uniquely

scope: small, duration: short-/medium, frequency: continously

Fenster schliessen

The project sponsor has just signed the project charter. What is the NEXT thing to
do?

Verify scope

Begin to complete work packages

Start to create management plans

Start integrated change control