x

Patrik Steuer

Patrik Steuer

Kartei Details

Karten 39
Sprache English
Kategorie BWL
Stufe Universität
Erstellt / Aktualisiert 07.12.2013 / 10.06.2015
Weblink
https://card2brain.ch/box/itm750chap06timemanagement
Einbinden
<iframe src="https://card2brain.ch/box/itm750chap06timemanagement/embed" width="780" height="150" scrolling="no" frameborder="0"></iframe>
Activity list

Tabulation of activities with name, ID, brief description

Activity attributes

Schedule related information such as predecessors, logical relationships, resource requirements, constraints, imposed dates ?

Milestone

Several different activities or significant event, black Diamond symbol

Slipped Milestone

Milestone was completed later than originally planed, white Diamond symbol

SMART criteria

Specific, Measurable, Assignable, Realistic, Time-framed

Mandatory dependencies

Hard logic dependencies, you cannot test code before it is written

Discretionary dependencies

Defined by the project team, for example good practices, soft logic should use with care because they may limit scheduling options

External dependencies

Relationship between project and non project tasks. You need hardware even if it is not part of your project scope to install new software.

Burst

Two or more activities follow a single node

Merge

Two or more acitivities have the same single node

Finish-to-Start

You cannot start activity B before activity A is finished

Start-to-Start

You cannot start activity B before activity A is started

Finish-to-Finish

You cannot finish activity B before activity A is finished

Start-to-Finish

You cannot finish activity B before activity A is started

Resource Breakdown structure

Hierarchical structure that identifies the project?s resources by category and type.

Effort

Number of workdays or work hours required to complete task.

Duration

Time worked on an activity plus elapsed time. F.E. working time is 1 hour but you have to wait 2 hours until you have additional information ? so it is 3 hours

Three-point estimate

Includes a optimistic, most likely and pessimistic estimate. It is required for performing PERT estimates.

Baseline dates

The planed schedule dates

Schedule baseline

Approved planed schedule

Critical path analysis

Network diagramming technique used to predict total project duration

Critical path

Series of activities that determine the earliest time the project can be completed.

Total Slack or Total float

Time an activity can be delayed without an delay for the project end.

Free Slack or Free float

Time an activity can be delayed without an delay for the immediately following activity

Early start date

Is the earliest possible time to start an activity based on project network logic

Early finish date

Is the earliest possible time to finish an activity based on project network logic

Forward pass

Determines the early start and early finish dates for each activity

Backward pass

Determines the late start and late finish dates for each activity

Late start date

Latest date at which an activity can be started without a delay the for project end

Crashing

Aktivitten mglichst verkrzen z.b. durch mehr Ressourcen um Zeit zu sparen

Fast tracking

Doing activities in parallel that you would normally do in sequence

Critical Chain scheduling

Scheduling considers limited resources. It removes buggers from individual tasks and creates a project buffer

Multitasking

One resource works on more than one task at a time, which increase avg. time

Project buffer

A time buffer for the hole project

Murphy?s Law

When something go wrong, it will.

Feeding Buffer

Additional buffer for the critical chain before they proceed on non-critical-path

Parkinson?s Law

Work expands to file the time allowed

Probabilistic time estimates

Duration estimates based on different guesses instead of a specific one

PERT weighted average

Duration based on (optimistic time + 4 * most likely time + pessimistic time) / 6