x
Kartei Details
Karten | 39 |
---|---|
Sprache | English |
Kategorie | BWL |
Stufe | Universität |
Erstellt / Aktualisiert | 07.12.2013 / 10.06.2015 |
Weblink |
https://card2brain.ch/box/itm750chap06timemanagement
|
Einbinden |
<iframe src="https://card2brain.ch/box/itm750chap06timemanagement/embed" width="780" height="150" scrolling="no" frameborder="0"></iframe>
|
Tabulation of activities with name, ID, brief description
Schedule related information such as predecessors, logical relationships, resource requirements, constraints, imposed dates ?
Several different activities or significant event, black Diamond symbol
Milestone was completed later than originally planed, white Diamond symbol
Specific, Measurable, Assignable, Realistic, Time-framed
Hard logic dependencies, you cannot test code before it is written
Defined by the project team, for example good practices, soft logic should use with care because they may limit scheduling options
Relationship between project and non project tasks. You need hardware even if it is not part of your project scope to install new software.
Two or more activities follow a single node
Two or more acitivities have the same single node
You cannot start activity B before activity A is finished
You cannot start activity B before activity A is started
You cannot finish activity B before activity A is finished
You cannot finish activity B before activity A is started
Hierarchical structure that identifies the project?s resources by category and type.
Number of workdays or work hours required to complete task.
Time worked on an activity plus elapsed time. F.E. working time is 1 hour but you have to wait 2 hours until you have additional information ? so it is 3 hours
Includes a optimistic, most likely and pessimistic estimate. It is required for performing PERT estimates.
The planed schedule dates
Approved planed schedule
Network diagramming technique used to predict total project duration
Series of activities that determine the earliest time the project can be completed.
Time an activity can be delayed without an delay for the project end.
Time an activity can be delayed without an delay for the immediately following activity
Is the earliest possible time to start an activity based on project network logic
Is the earliest possible time to finish an activity based on project network logic
Determines the early start and early finish dates for each activity
Determines the late start and late finish dates for each activity
Latest date at which an activity can be started without a delay the for project end
Aktivitten mglichst verkrzen z.b. durch mehr Ressourcen um Zeit zu sparen
Doing activities in parallel that you would normally do in sequence
Scheduling considers limited resources. It removes buggers from individual tasks and creates a project buffer
One resource works on more than one task at a time, which increase avg. time
A time buffer for the hole project
When something go wrong, it will.
Additional buffer for the critical chain before they proceed on non-critical-path
Work expands to file the time allowed
Duration estimates based on different guesses instead of a specific one
Duration based on (optimistic time + 4 * most likely time + pessimistic time) / 6