Project Management for Construction Projects
ETHZ / HS2022 / Bauingenieurwissenschaften Master / Project Management for Construction ProjectsWith this and the kahoot multiple choice questions you're good to go! 5.0 guaranteed!
ETHZ / HS2022 / Bauingenieurwissenschaften Master / Project Management for Construction ProjectsWith this and the kahoot multiple choice questions you're good to go! 5.0 guaranteed!
Fichier Détails
Cartes-fiches | 94 |
---|---|
Langue | English |
Catégorie | Gestion d'entreprise |
Niveau | Université |
Crée / Actualisé | 24.11.2022 / 28.12.2022 |
Lien de web |
https://card2brain.ch/box/20221124_project_management_for_construction_projects
|
Intégrer |
<iframe src="https://card2brain.ch/box/20221124_project_management_for_construction_projects/embed" width="780" height="150" scrolling="no" frameborder="0"></iframe>
|
Project Monitoring
Project monitoring is the activity of overseeing all tasks and actively paying attention to the project process in order to guarantee that the project is implemented as planned.
Can help to identify potential risks and deviations in time and initiate countermeasures.
Quality-based performance excellence models
European Foundation for Quality Management (EFQM)
- a holistic view of the organization
- the aim is to develop an excellent organization
Baldrige Criteria for Excellence
- used in the United States
- to improve their overall performance
- an integrated approach to delivering ever-improving products and services to the costumers
KPI
Key Performance Indicators
- A measurable value that demonstrates how effectively a company is performing
- To control and evaluate the performance of different projects or departments
- Depending on the perspective, different KPIs are used
e.g. marketing --> number of new customers, construction team --> piles build
Three known types of KPIs:
- Output factors
--> what is done - Input factors
--> what is needed - Hardship factors
--> beyond the control of the project manager (e.g. weather)
Earned value analysis (EVA)
The EVA is a method used for project controlling.
- measure progress at any given point in time
- determines the schedule, cost, and performance deviations
and their dependencies between them
Use in different phases:
- During planning phase
determine the cash flow requirements
- During bidding phase
used by the contractor to compare different cash flow projections using different progress scenarios
- During construction phase
used as a control tool to monitor the actual progress in comparison with the initial plans
EVA - BCWS
Budgeted cost of work scheduled
a.k.a. planned value (PV)
= total cost * % planned work
EVA - ACWP
Actual cost of work performed
a.k.a. actual cost (AC)
= what is paid for an activity
EVA - BCWP
Budgeted cost of work performed
a.k.a. earned value (EV)
= total cost * % work done
Estimate to complete (ETC)
The expected cost needed to complete all the remaining work in the project.
Original estimate ECT = BAC - BCWP
Cost deviation accounted ECT = (BAC - BCWP) / CPI
Estimate at completion (EAC)
The expected total cost of the project.
EAC = ACWP + ECT = BAC - CV
EVA - disadvantages
Critical path ignorant
SPI is not intuitive (measures SPI in cost and not units of time)
Needs a lot of information
Difficult to implement (need to track costs and progress, %completion hard to track)
Quality Management
It includes all the processes and activities that determine quality policies, objectives, and responsibilities so that the project will satisfy the needs, for which it was undertaken.
Quality assurance
Planned systematic actions established to get a level of confidence that project design documents comply with applicable codes and criteria and that the resulting construction complies with the contract documents.
Cost of Quality
Aims of Risk Management
Aims to:
- increase the probability and impact of positive events
- decrease the probability and impact of negative events
- to create value
resources expended to mitigate risk should be less than the consequence of inaction
Risk Management Process (6 Steps)
1. Plan risk management
2. Identify risk
3. Qualitative analysis
4. Quantitative analysis
5. Plan risk response
6. Monitor and control risk
Risk register
The identified risks are summarized in a risk register (or risk portfolio).
After identifying the risks, the risks need to be described in as much detail as is reasonable.
Risk Analyis
Qualtitative Risk Analyis
- used for initial assessments (fast and not much data needed)
- based on subjective opinions --> very dependent on the expert's opinions
- a prioritization of risk reduction measures is difficult
Quantitative Risk Analysis
- most important risks (established with quantitative RA) are further examined
- data needed
- developed model should always be validated
- Approaches:
- expected values
- decision trees
- simulations (e.g. Monte-Carlo)
- etc..
Risk Response
Strategies to reduce the risks to an acceptable level.
Reaction options to negative risk:
- Acceptance
- Avoidance
- Mitigation / Reduction
- Transfer of risks
Reaction options to negative risk (opportunities):
- Exploiting (eliminate uncertainty --> ensure it happens)
- Sharing (involve a third party who is best able to capture the opportunity)
- Enhancing (increase probability or impact)
- Accepting (not actively pursue it)
Project Closeout
The closeout is the last subphase of the construction/implementation phase of a project.
Is often not properly carried out --> leads to discontent
Includes
- Handover of the project to the end client
- removal of defects
- final invoices for the contractors
- check if every contractor completed their work
Project Closeout Process (5 Steps)
- Project closeout
- Client closeout
- Organisational closeout
- Final report
- Team closeout
Stakeholder
A stakeholder is a person or an entity, which is involved in or affected by a project.
Some might even have influence on the project.
Distinctions:
- Direct stakeholders: directly associated or involved
- Indirect stakeholders: indirectly (e.g. national or local government)
- Positive stakeholders: likely to have a favourable impact
- Negative stakeholders: likely to have a detrimental impact
Stakeholder Management - 5-step-approach
1. Identify stakeholders
2. Plan communication
3. Distribute information
4. Manage expectations
5. Report performance
Communication plan
Interpersonal Skills
As a project manager, not only competent knowledge but also social and interpersonal skills are important.
- Team building
- Motivation
- Communication
- Influence
- Decision-making
- Political and cultural awareness
- Negotiation
Agile Project Management
Agile project management
- iterative and incremental approach
- instead of sticking to a pre-defined plan
--> tries to flexibly respond to changes and uncertainties during a project - these responses are done with a step-by-step approach
- all about efficient communication
- instead of insisting on pre-defined processes
--> work procedure, which suits the participating individuals the most
Lean construction
"A way to design production systems to minimise waste of materials, time, and effort in order to generate the maximum possible amount of value."
"Just-in-time" concept:
To only produce "what is needed, when is needed, and in the amount is needed."
"Jidoka" concept:
Can be loosely translated as "automation with a human touch" and means that the equipment stops immediately when a problem in the production line occurs, thereby preventing defective products from being produced and allowing the workers to directly solve the problem.
Steps to generate value (Toyota, 1991)
1. Identify customers and specify value
2. Identify and map the value stream
3. Create flow by eliminating waste
4. Respond to customer pull
5. Pursue perfection (iterative process --> cycle begins again)
5S - Technique
Lean technique for how a workspace can be efficiently and effectively organised.
Sort (sorting out all unnecessary items at a location)
Straighten (creating a smooth, straight workflow)
Shine (cleaning and inspecting on a regualr basis)
Standardise (standardisation of the first three "S" pratices)
Sustain (sustaining the established processes through self-discipline)
5 Whys - Technique
A lean technique used to identify the cause-and-effect relationships regarding a particular problem.
Principles for Lean Construction
Improving communication and promoting collaboration
Eliminating waste and errors
Direct intervention to drive immediate and apparent change
Improving work planning and forward scheduling
Specifying value from the perspective of the costumer
Identify the processes that deliver costumer value (the value stream)
Ensuring the work environment is clean and safe
Forms of waste
Time (looking for things, ordering materials)
Transport (materials, handling deliveries)
Staff downtime (waiting for instructions, information and deliveries)
Rework and corrections (correcting poor or incorrect work and updating plans)
Overproduction (producing more than needed)
Inventory (too much or too little stock on hand)
Lean Project Delivery System (LPDS)
Following features of the LPDS are essential:
- the project is structured and managed as a value generating process
- project control has the job of execution instead of reliance on after-the-fact variance detection
- optimisation efforts are focused on making workflow reliable instead of improving productivity
- pull techniques are used to govern the flow of materials and information
- capacity and inventory buffers are used to absorb variability
- feedback loops are incorporated at every level, dedicated to rapid system adjustment
Last Planner System
- Collaborative and iterative project planning system
- Planning takes place on different process levels
- should yield to a completion of the project
because problems are discovered and solved before they become an impairment - results in a more reliable schedule
because the people, which actually do the work, are directly involved in the planning
What is Project Management?
Project management is the discipline of initiating, planning, executing, controlling, and closing the work of a team to achieve specific goals and meet specific success criteria.
What is a project?
A project is an organized effort with a specific goal.
Project phases
General definition:
- Starting the project
- Organizing and preparing
- Carrying out the project work
- Closing the project
According to SIA 112:
- Strategic planning
- Definition of needs, solution strategies
- Preliminary studies
- Project definition, feasibility study
- Selection procedures
- Project development
- Preliminary project
- Construction project
- Permit-obtaining procedure / submitted project
- Invitation to Bid
- Invitation to bid, comparison of quotations
- Construction / Implementation
- Construction project
- Implementation
- Commissioning, completion
- Management
- Operation
- Maintenance