Every Scrum Team must have a Product Owner and Scrum Master.

Five new Scrum Teams have been created to build one product. A few of the developers on one of the Development Teams ask the Scrum Master how to coordinate their work with the order teams. What should the Scrum Master do?

For the purpose of transparency, when does Scrum say a new increment of working software must be available?

For which is the Scrum Master responsible?

How can a Product Owner use time-boxed Sprints to obtain feedback from users and the market?

How does an organization know that a product built through Scrum is successful?

How important is it for a Product Owner to order Product Backlog items by value points?

How is management external to the Scrum Team involved in the Daily Scrum?

How many hours per day should a person on a Scrum Team work?

How much of the Sprint Backlog must be defined during the Sprint Planning meeting?

How much time is required after a Sprint to prepare for the next Sprint?

How much time must a product owner spend with the Development Team?

How much work must a Development Team do to a Product Backlog item it selects for a Sprint?

How often should customer satisfaction be measured?

How often should Development Team membership change?

How should a Development Team deal with non-functional requirements?

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?

How small should a 'ready' Product Backlog item be?

If burn-down charts are used to visualize progress, what do they track?

If burn-down charts are used to visualize progress, what does a trend line through a release burn-down chart indicate?

If quality assurance work does not occur as part of the development work within a Sprint, which benefits are lost?

If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?

In accordance with Scrum theory, how should a group of 100 people be divided into multiple Development Teams?

In order to achieve the benefits of Scrum, it is important to enact the value of commitment. What two actions demonstrate the commitment of Scrum Team members?

In order to make investment decisions, the Product Owner is likely to look at the Total Cost of Ownership (TCO) of the product being built. What costs will a Product Owner take into account?

In order to maximize the value of the product, a Product Owner needs awareness of the following:

In the middle of the Sprint, the customer decides that there are 2 new features she wants. The Product Owner should...

In the Sprint Planning meeting, the Product Owner and the Development Team were unable to reach a clear understanding about the highest order Product-Backlog items. Because of this, the Development Team couldn't figure out how many Product Backlog items it could forecast for the upcoming Sprint. They were able to agree on a Sprint Goal, however. Which of the following two actions should the Scrum Master support?

It is mandatory for the Product Owner to monitor and share progress of Product Backlog through...

It is mandatory that the product increment be released to production at the end of each Sprint.

Items on the Product Backlog tend to be...

Learning turns into 'validated learning' when assumptions and goals can be assessed through results. What is a key way for a Product Owner to apply validated learning?

Multiple Scrum Teams working on the same product or system all select work from the same Product Backlog.

Must the Product Owner be present at the Sprint Retrospective?

One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum?

Product Owners must specify complete acceptance criteria for product Backlog item before the team can select the item in Sprint Planning.

Scrum has a role called "Project Manager".

Scrum is a methodology that tells in detail how to build software incrementally.

Scrum is based on empirical process control theory. All of its artifacts must be transparent to ensure sufficient accuracy of inspection. Select two ways to maintain the product backlog to maximize its transparency?

Scrum is based on empirical process control theory. All of its artifacts must be transparent to ensure sufficient accuracy of inspection. Which two measures ensur that the product backlog is transparent?