LaLiDa
Scrum
Scrum
Fichier Détails
Cartes-fiches | 318 |
---|---|
Utilisateurs | 64 |
Langue | English |
Catégorie | Gestion d'entreprise |
Niveau | Autres |
Crée / Actualisé | 08.06.2020 / 24.05.2024 |
Lien de web |
https://card2brain.ch/box/20200608_lalida
|
Intégrer |
<iframe src="https://card2brain.ch/box/20200608_lalida/embed" width="780" height="150" scrolling="no" frameborder="0"></iframe>
|
3.
Which statement is least accurate about the definition of "Done"?
4.
It is forecasted that the project will be over in 4 Sprints. The Product Owner wants to design an acceptance test for all items. What´s the best response from the Scrum Master?
5.
Which of the following are optional in Scrum? (Two answers)
6.
Which of the following is the most important opportunity for capturing lessons learned?
7.
Which of the following is a valid service the Scrum Master to the Product Owner?
8.
Scrum is an iterative and incremental Agile process.
9.
There are 6 teams working on the same product. How many Product Owners do they need?
10.
Development Team members should be cross-functional.
11.
Revenue generation is the primary factor in determining value.
12.
Who can change the Sprint Backlog during the Sprint?
13.
What is the most important metric for a Product Owner to measure, in order to make the progress of the project clear?
14.
The Product Owner is not sure about sustainability of the current velocity when s/he´s calculating the completion date. What can be the reason?
15.
The Product Owner is accountable for the end result and therefore should have the final say over the definition of "Done".
16.
All interactions between the stakeholders and the Development Team should be through the Product Owner.
17.
Which two statements are correct during the Sprint?
18.
Self-organizing teams are characterized by their ability to ...
19.
Time can be allocated between the two Sprints for integration.
20.
What is typical work for the Product Owner between the end of the Sprint Planning and before the Review? (Three answers)
21.
The Development Team cannot deliver the Increment because they don't understand a functional requirement. What should they do?
22.
Who monitors the remaining work of the Product Backlog?
23.
A Product Owner Should handle all the responsibilities of a traditional project manager.
24.
How should developers deal with non-functional features?
25.
What should the Product Owner do in the middle of the Sprint, when the Development Team realizes they are not able to finish all the Sprint Backlog items?
26.
The number of developers has increased from 7 to 14. Now the Daily Scrum does not fit in 15 minutes. What´s the best response to this problem?
27.
The Product Owner must provide transparency into the project status by ...
28.
The Sprint Review is the only time when stakeholder feedback is captured.
29.
How are Product Backlog items selected in scaled Scrum?
30.
The Product Owner has doubts about the quality of the definition of "Done". What should she do?
31.
The Development Team is ready to start the first Sprint, while the Product Backlog is not complete yet. What should the Product Owner do?
32.
Who owns the Sprint Backlog?
33.
The Product Owner can Transfer some of his/her accountability to the developers.
34.
Which if the following are optional in Scrum (Two answers)
35.
Which statement is correct when multiple Scrum teams are working on the same product?
36.
Pick 3 activities that can be the responsibilities of the Product Owner.
37.
What happens to the product Backlog when the end-users environment and needs change in the middle of the project?
38.
The Product Owner can delegate some of his/her responsibilities to the Development Team.
39.
Which options are acceptable when the Product Owner wants to be informed of the progress in the middle of the Sprint? (two answers)
40.
The items selected from the Product Backlog for the Sprint backlog should be "ready".
41.
What are the benefits of having a solid product vision?
42.
It´s better to have longer Sprints when the project is riskier.