FOR THE DEVELOPMENT OF A GANTT CHART THE FOLLOWING INFORMATION
AMONG OTHERS IS REQUIRED..

detailed resource interdependencies

information about time reserves

duration of the work packages

cost caluctaion

Fenster schliessen

PROJECT COSTS

are calculated at the first mile stone of the project.

are calculated by the project owner team.

cannot be planned at the beginning of a project.

can be differentiated in cost types

Fenster schliessen

A PROJECT RISK ANALYSIS…

is the basis fort he work breakdown stucture

has to be done by the project manager alone

is part of the project close down report.

is the basis for planning corrective and preventive measures

Fenster schliessen

DURING THE PROJECT COORDINATION PROCESS …

a project progress report is developed.

the project team members will be selected

the project assignment will be finalized

the project manager accepts work package results.

Fenster schliessen

THE FREQUENCY OF PROJECT MEETINGS DEPEND ON …

the complexity of the project.

the number of project owners.

the objects of consideration of the project.

the number of available meeting rooms.

Fenster schliessen

METHODS FOR PROJECT COORDINATION ARE AMONG OTHERS:

project status report

to-do and decision lists

project score card

project risk register

Fenster schliessen

OBJECTS OF CONSIDERATION OF PROJECT CONTROLLING ARE AMONG OTHERS:

project schedule

project network

project portfolio

project database

Fenster schliessen

PROJECT CONTROLLING …

is performed continuously

is performed at the end of the project

adaptes the project network

is performed only by the project owner team.