A WORK BREAKDOWN STRUCTURE …

is only used in plant construction projects.

is a method of scheduling.

should be done by the project manager alone

is a central communication instrument.

Fenster schliessen

A WORK BREAKDOWN STRUCTURE …

is the basis for the scheduling, cost and resource planning.

is developed during the project controlling process.

segments the objects of consideration of the project.

is a project organisation chart.

Fenster schliessen

THE OBJECTIVES OF WORK BREAKDOWN STRUCTURING ARE AMONG OTHERS …

the development of a communication instrument.

the planning of project schedules.

the planning of project costs and project resources.

the definition of the project communication structures.

Fenster schliessen

THE DEVELOPMENT OF A WORK BREAKDOWN STRUCTURE …

helps to create a common project understanding.

must be repeated each time the schedule is changed.

should be defined by the project owner.

has to be done after the schedule, cost and resource planning.

Fenster schliessen

WORK PACKAGE SPECIFICATIONS ...

give orientation for the work of the project team members.

supports the project portfolio coordination

should be defined by the project owner.

has to be done after the schedule, cost and resource planning.

Fenster schliessen

WORK PACKAGE SPECIFICATIONS ...

helps to create a common project understanding.

must be repeated each time the schedule is changed.

should be defined by the project owner.

has to be done after the schedule, cost and resource planning.

Fenster schliessen

A GANTT CHART IS…

an important communication instrument in project management.

a list of milestones.

a project plan which is difficult to read.

less user-friendly than the cpm.

Fenster schliessen

A GANTT CHART IS…

a graphic representation of the project resources in bar-chart form.

graphic representation of the project which depicts the work packages as timeproportional bars.

a graphic representation of the project costs in bar-chart form.

a graphic representation of the relevant project environments in bar-chart form.