Processe(s) of Project Integration Management in initiating phase?
- Develop project charter
Processe(s) of Project Integration Management in planning phase?
- Develop project management plan
Processe(s) of Project Integration Management in executing phase?
- Direct and manage project work
Processe(s) of Project Integration Management in monitor and control phase?
- Monitor and control project work,
- Perform integrated change control
Processe(s) of Project Integration Management in closing phase?
- Close project or phase
The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to applay organizational resources to project activities.
Inputs of develop project charter process?
- Aggrements,
- Project Statement Of Work (SOW),
- Business Case,
- EEF,
- OPAs
Tools and techniques of develop project charter process?
- Expert judgment,
- Facilitation techniques
Outputs of develop project charter process?
- Project charter
The process of defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan. The projectÕs integrated baselines and subsidiary plans may be included within the project management plan.
Inputs of develop project management plan process?
- Project charter,
- Output form other processes: plans, process improvment plan, requirement management plan (Business Analyst), baseline(scope, cost, schedule),
- project management plan updates,
- EEF,
- OPAs
Tools and techniques of develop project management plan process?
- Expert judgment,
- Facilitation techniques
Outputs of develop project management plan process?
- Project management plan
The process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the projectÕs objectives.
Inputs of Direct and manage project work process?
- Project management plan,
- Approved change requests,
- EEF,
- OPAs
Tools and techniques of Direct and manage project work process?
- Expert judgment,
- Project Management Information System (PMIS),
- Meetings
Outputs of Direct and manage project work process?
- Deliverables,
- Work performance data,
- Change requests,
- Project management plan updates,
- Project documents updates
The process of tracking, reviewing, and reporting project progress against the performance objectives defined in the project management plan.
Inputs of monitor and control project work process?
- Project management plan,
- Forecasts(schedule, cost),
- Validate changes,
- Work performance information,
- EEF,
- OPAs
Tools and techniques of monitor and control project work process?
- Expert judgment,
- Analytical techniques,
- Project Management Information System (PMIS),
- Meetings
Outputs of monitor and control project work process?
- Change requests,
- Work performance reports,
- Project management plan updates,
- Project documents updates
The process of reviewing all change requests, approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan, and communicating their disposition.
Inputs of perform intagrated change control process?
- Project management plan,
- Work performance reports,
- Change requests,
- EEF,
- OPAs
Tools and techniques of perform intagrated change control process?
- Expert judgment,
- Meetings,
- Change control tools
Outputs of perform intagrated change control process?
- Approved change requests,
- Change log,
- Project managemnet plan updates,
- Project documents updates
The process of finalizing all activities across all of the Project Management Process Groups to formally complete the phase or project.
Inputs of close project of phase process?
- Project managment plan,
- Accepted deliverables,
- OPAs
Tools and techniques of close project of phase process?
- Expert judgment,
- Analytical techiques,
- OPAs updates
Outputs of close project of phase process?
- Final product, service or result transition,