What are the major processes of Project Scope Manageemnt and their phases?
- Plan Scope Management (Plan)
- Collect Requirements (Plan)
- Define Scope (Plan)
- Create WBS (P)
- Validate Scope(M&C)
- Control Scope (M&C)
What are the inputs of the Plan Scope Management process?
- Project Management Plan
- Project Charter
- EFFs
- OPAs
What are the tools & techniques of the Plan Scope Management process?
- Expert Judgement
- Meetings
What are the outputs of the Plan Scope Management process?
- Scope Management Plan
- Requirements Management Plan
What are the inputs to the Collect Requirements process?
- Scope Management Plan
- Requirements Management Plan
- Stakeholder Management Plan
- Project Charter
- Stakeholder Register
What are the tools & techniques to the Collect Requirements process?
- Interviews
- Focus Groups
- Facilitated workshops
- Group creativity techniques
- Group decision-making techniques
- Questionaires and surveys
- Observations
- Prototypes
- Benchmarking
- Context Diagrams
- Document Analysis
What are the outputs to the Collect Requirements process?
- Requirements Documentation
- Requirements traceability matrix
What are the inputs to the Define Scope process?
- Scope Management Plan
- Project Charter
- Requirements Documentation
- OPAs
What are the tools & techniques to the Define Scope process?
- Expert Judgement
- Product Analysis
- Alternatives generation
- Facilitated workshops
What are the outputs to the Define Scope process?
- Project Scope Statement
- Project Documents Updates
What are the inputs to the Create WBS process?
- Scope Management Plan
- Project Scope Statement
- Requirements Documentation
- EEFs
- OPAs
What are the tools & techniques to the Create WBS process?
- Decomposition
- Expert Judgement
What are the outputs to the Create WBS process?
- Scope Baseline
- Project documents updates
What are the inputs to the Validate Scope process?
- Project Management Plan
- Requirements Documentation
- Requirements Traceability Matrix
- Verified Deliverables
- Work Performance Data
What are the tools & techniques to the Validate Scope process?
- Inspection
- Group decision-making techniques
What are the outputs to the Validate Scope process?
- Acceptable deliverables
- Change requests
- Work Performance Information
- Project Documents Updates
What are the inputs for the Control Scope process?
- Project Management Plan
- Requirements Documentation
- Requirements Traceability Matrix
- Work Performance Data
- OPAs
Variance Analysis
What are the outputs for the Control Scope process?
- Work Performance Information
- Change Requests
- Project mananagement plan updates
- Project documents updates
- OPAs