Kostenberechnung PM
Projektmanagement Kostenberechnungen
Projektmanagement Kostenberechnungen
Set of flashcards Details
Flashcards | 8 |
---|---|
Language | Deutsch |
Category | Micro-Economics |
Level | University |
Created / Updated | 16.06.2015 / 16.12.2019 |
Licencing | Not defined |
Weblink |
https://card2brain.ch/box/kostenberechnung_pm
|
Embed |
<iframe src="https://card2brain.ch/box/kostenberechnung_pm/embed" width="780" height="150" scrolling="no" frameborder="0"></iframe>
|
Cost Variance CV
CV= EV-AC (A negative value signifies a budget overrun)
Schedule Variance SV
SV= EV-PV (A negative value signifies a schedule delay)
Cost Performance Index CPI
CPI= EV/AC (Each invested Euro returns a CPI fraction thereof. Is widely used to forecast costs at project completion)
Schedule Performance Index SPI
SPI= EV/PV The project is SPI % completed compared to plan. Is sometimes used in conjunction with the CPI to estimate the project completion
Estimate at Completion EAC
EAC= BAC/CPI (How much is the total project estimated to cost based on the current state of completion? )
Estimate to Completion ETC
ETC= EAC-AC (How much more will the project cost from this period on? )
Variance at Completion VAC
VAC= BAC-EAC (How large will the variance be at project completion? )
Estimate Total Duration ETD
ETD= Planned Duration/SPI (Based on todays status, how long will the total project last? )