Professional Scrum Master
Fundamental level of Scrum mastery
Fundamental level of Scrum mastery
Kartei Details
Karten | 136 |
---|---|
Lernende | 65 |
Sprache | English |
Kategorie | Informatik |
Stufe | Andere |
Erstellt / Aktualisiert | 17.04.2020 / 17.06.2025 |
Weblink |
https://card2brain.ch/box/20200417_professional_scrum_master
|
Einbinden |
<iframe src="https://card2brain.ch/box/20200417_professional_scrum_master/embed" width="780" height="150" scrolling="no" frameborder="0"></iframe>
|
Lernkarteien erstellen oder kopieren
Mit einem Upgrade kannst du unlimitiert Lernkarteien erstellen oder kopieren und viele Zusatzfunktionen mehr nutzen.
Melde dich an, um alle Karten zu sehen.
The Product Owner manages the Product Backlog. Who is accountable for estimating the effort to complete the Product Backlog items?
The value delivered by a product can only be determined by revenue.
How does an organization know that a product built through Scrum is successful?
The process of regular inspection and adaptation employs knowledgable and skilled inspectors. What are two ways in which the Product Owner takes the lead in the inspection process?
(choose the best two answers)
What is the Product Owner accountable for in Scrum?
A Product Owner is entitled to postpone the start of a new Sprint after the conclusion of a previous Sprint for the following reason:
Learning turns into 'valitated learning' when assumptions and goals can be assessed through results. What is a key way for a Product Owner to apply validated learning?
In order to make investment decisions, the Product Owner is likely to look at the Total Cost of Ownership (TCO) of the product being built. What costs will a Product Owner take into account?
Must the Product Owner be present at the Sprint Retrospective?
When can the Product Backlog be updated?
What is a Product Backlog?
Which two things does the Development Team do during the first Sprint?
Choose the best two answers
Which statement best describes Scrum?
The CEO asks the Development Team to add a "very important" item to a Sprint that is in progress. What should the Development Team do?
When might a Sprint be abnormally cancelled?
What are the three fundamentals of empirical work?
- transparency
- investigation
- adaption
What are the 5 values of Scrum?
- commitment
- focus
- openness
- respect
- courage
What are the roles of a Scrum team?
- Product Owner
- Scrum Master
- Development team
How many members does a Scrum team have?
3-9
What are the events that occur when doing Scrum?
- Sprint Planning
- Daily Scrum
- Sprint Review
- Sprint Retrospective
How long is a Daily Scum?
max 15 minutes
How long is a Sprint Planning?
max. 8h
How long is a Sprint Retrospektive?
max. 3h
How long is a Sprint Review?
max. 4h
How long is a Sprint?
max. 4 weeks
How much days are between Sprints?
0
What are the Scrum artefacts?
- Product Backlog
- Sprint Backlog
- Increment
What are the pillars of the Toyota way of thinking?
- continous improvement (Kaizen)
- respect the people
What are the 4 values that are written down in the agile manifesto?
- Individuals and Interactions over Processes and Tools
- Working Software over Comprehensive Documentation
- Customer Collaboration over Contract Negotiation
- Responding to Change over Following a Plan
What are the 5 domains of the Cynefin Framework?
- obvious
- complicated
- complex
- chaotic
- disorder
-