V06 Scheduling and Costing
Approaches to designing schedules: - Milstones - Illustration methods - Forward, backward passes -> critical path Approaches to designing costs: - Different kinds of costs
Approaches to designing schedules: - Milstones - Illustration methods - Forward, backward passes -> critical path Approaches to designing costs: - Different kinds of costs
-
- 1 / 15
-
Flashcards
What Points are included in BCC2 "Building"?
- Basement excavation
- Structure
- Electrical installations
- HVAC installations
- Sanitary installations
- Transport installations
- Finishing Work
A: Hostel
- No reserves
B: Hospital refurbishment
- High Preparatory work -> refurbishment
- High Costs for public procurement and credit -> public building
-
C: Hospital / School new building?
- High Reserves -> Public building?
- Lower Preparatory work than refurbishment
D: Hotel
- High Furnishing cost
- High External Cost (Garden)
There are different types of costing depending on which project delivery phase it is made. Name them with its accuracy.
Draw a graph of the costings depending on the project delivery phase and level of detail.
Name 4 Methods of costing
- By Elements
- By Modules
- My Trades and Works
- By Volume and Area
What percentage is the building cost approximately relative to the total production cost?
Building Cost ca. 90% of the Production cost.