Lernkarten

Karten 63 Karten
Lernende 6 Lernende
Sprache English
Stufe Universität
Erstellt / Aktualisiert 07.01.2020 / 08.01.2020
Lizenzierung Keine Angabe
Weblink
Einbinden
0 Exakte Antworten 0 Text Antworten 63 Multiple Choice Antworten
Fenster schliessen

Constraction contracts include the destruction of an asset

True

False

Fenster schliessen

Under IAS 11, two or more contracts should be accounted for separately, even if they were negotiated together

True

False

Fenster schliessen

What isn't obligatory to determine if the construction of a series of assets should be treated as separate contracts?

Separate proposals were submitted 

The customer could use different contractors for each asset 

Contracts will run concurrently or in a single sequence 

Costs and revenues can be separated for each asset 

Fenster schliessen

A fixed price contract is a contract in which the contractor agrees to a

Fixed contract price, but must bear the escalation costs

Fixed contract price which might be subject to escalation costs 

Fixed rate per unit of output which is not subject to escalation costs 

Fixed rate per unit of output and bears escalation costs

Fenster schliessen

Which of the following costs cannot be allocated to a construction contract cost?

Material used in construction 

Rectification work 

Design work

Selling costs

Fenster schliessen

Architects fees for the construction of a building should not be accounted for under IAS 11

True

False

Fenster schliessen

A contract in which the contractor agrees to a pre-determined contract price

Fixed price contract

Pre-defined contract 

Cost plus contract 

Negotiated contract 

Fenster schliessen

A contract in which the contractor is reimbursed for pre-defined costs, plus a percentage

Fixed price contract

Pre-defined contract 

Cost plus contract 

Negotiated contract