SAT 7
Self Assesment Test 7 in PMI
Self Assesment Test 7 in PMI
Kartei Details
Karten | 31 |
---|---|
Lernende | 25 |
Sprache | Deutsch |
Kategorie | Informatik |
Stufe | Universität |
Erstellt / Aktualisiert | 26.10.2019 / 14.01.2021 |
Weblink |
https://card2brain.ch/box/20191026_sat_7
|
Einbinden |
<iframe src="https://card2brain.ch/box/20191026_sat_7/embed" width="780" height="150" scrolling="no" frameborder="0"></iframe>
|
Lernkarteien erstellen oder kopieren
Mit einem Upgrade kannst du unlimitiert Lernkarteien erstellen oder kopieren und viele Zusatzfunktionen mehr nutzen.
Melde dich an, um alle Karten zu sehen.
Which of the following represents the estimated value of the work actually
accomplished?
A ... compares the amount of the contingency reserves remaining to the
amount of risk remaining at any time in the project in order to determine if
the remaining reserve is adequate.
One common way to compute estimate at completion (EAC) is to take the
budget at completion (BAC) and:
A cost performance index (CPI) of 0.89 means:
If earned value (EV) = 350, actual cost (AC) = 400, planned value (PV) = 325, what is
the cost variance (CV)?
Which of the following is NOT a task of the Close Project phase?
Which of the following is NOT a task of the process 'Close Project or Phase'?
If earned value (EV) = 400, actual cost (AC) = 350, planned value (PV) = 325, what is the cost variance (CV)?
Which one of the following processes is NOT part of the Monitoring & Controlling Process Group?
Which of the following formulas is not correct?
Which processes are not contained by the Monitoring and Controlling Process Group?
The final project report contains ...
Validate Scope is is in the same process group as
If earned value (EV) = 400, actual cost (AC) = 350, planned value (PV) = 325, what is the schedule variance (SV)?
If earned value (EV) = 400, actual cost (AC) = 350, planned value (PV) = 325, what is the cost variance (CV)?
Which one of the following is NOT a technique/ tool of the Control Risks process?
Budget at Completion (BAC) ...
Which of the following is a task of the process 'Close Project or Phase'?
A schedule performance index (SPI) of 0.76 means:
If earned value (EV) = 350, actual cost (AC) = 400, planned value (PV) = 325, what is the
schedule variance (SV)?
An output of the Close Project or Phase process is the creation of:
Which processes are contained by the Closing Process Group?
Estimate at completion (EAC) is a periodic evaluation of:
Which of the following is NOT a possible criteria for the weighting within a Relevance Tree?
The construction phase of a new software product is near completion. The next phases are
testing and implementation. The project is two weeks ahead of schedule. What should the
project manager be MOST concerned with before moving on to the final phase?
A Records Management System is ...
Directly before the process Control Costs starts, the process .... is executed.
Risk Audits ...
The final project report does NOT contain ...
A manufacturing project has a schedule performance index (SPI) of 0.89 and a cost
performance index (CPI) of 0.91. Generally, what is the BEST explanation for why this
occurred?
-
- 1 / 31
-