PMP Questions
Multipel Choice Questions for PMP Examination Sämtliche Fragen und Bilder stammen aus der Website http://www.misterexam.com/pmp
Multipel Choice Questions for PMP Examination Sämtliche Fragen und Bilder stammen aus der Website http://www.misterexam.com/pmp
Set of flashcards Details
Flashcards | 100 |
---|---|
Students | 24 |
Language | English |
Category | Micro-Economics |
Level | Other |
Created / Updated | 12.08.2013 / 06.06.2025 |
Weblink |
https://card2brain.ch/box/pmp_questions
|
Embed |
<iframe src="https://card2brain.ch/box/pmp_questions/embed" width="780" height="150" scrolling="no" frameborder="0"></iframe>
|
A schedule was developed for a project to install windows in an apartment building. The project is a rush job, and the contractor has agreed to schedule the work on a single shift basis but will work seven days per week until the job is done. The project is to begin on May 1. 42. What day in May will activity D have for its early finish date?
A schedule was developed for a project to install windows in an apartment building. The project is a rush job, and the contractor has agreed to schedule the work on a single shift basis but will work seven days per week until the job is done. The project is to begin on May 1. 43. What is the free float for activity F?
A schedule was developed for a project to install windows in an apartment building. The project is a rush job, and the contractor has agreed to schedule the work on a single shift basis but will work seven days per week until the job is done. The project is to begin on May 1. 44. What is the free float for activity D?
A schedule was developed for a project to install windows in an apartment building. The project is a rush job, and the contractor has agreed to schedule the work on a single shift basis but will work seven days per week until the job is done. The project is to begin on May 1. 45. What is the critical path of the project?
A schedule was developed for a project to install windows in an apartment building. The project is a rush job, and the contractor has agreed to schedule the work on a single shift basis but will work seven days per week until the job is done. The project is to begin on May 1. 46. What is the late start for activity F?
A schedule was developed for a project to install windows in an apartment building. The project is a rush job, and the contractor has agreed to schedule the work on a single shift basis but will work seven days per week until the job is done. The project is to begin on May 1. 47. How long is the project in days?
A schedule was developed for a project to install windows in an apartment building. The project is a rush job, and the contractor has agreed to schedule the work on a single shift basis but will work seven days per week until the job is done. The project is to begin on May 1. 48. What is the early start for activity F?
A schedule was developed for a project to install windows in an apartment building. The project is a rush job, and the contractor has agreed to schedule the work on a single shift basis but will work seven days per week until the job is done. The project is to begin on May 1. 49. If there is a delay in activity F of six days, what is the effect on the project completion date?
A schedule was developed for a project to install windows in an apartment building. The project is a rush job, and the contractor has agreed to schedule the work on a single shift basis but will work seven days per week until the job is done. The project is to begin on May 1. 50. What is the early finish date for activity A?
A schedule was developed for a project to install windows in an apartment building. The project is a rush job, and the contractor has agreed to schedule the work on a single shift basis but will work seven days per week until the job is done. The project is to begin on May 1. 51. The above diagram is called:
In a project to install concrete sewer lines there is a lot of uncertainty as to how long the durations should be for the tasks involved. The project manager has determined that the team will use the PERT technique to evaluate the project’s completion date. The diagram shows nine activities and the table shows the optimistic, pessimistic, and most likely estimates that the team has already made. 53. What is the expected value of the number of days to complete the project?
In a project to install concrete sewer lines there is a lot of uncertainty as to how long the durations should be for the tasks involved. The project manager has determined that the team will use the PERT technique to evaluate the project’s completion date. The diagram shows nine activities and the table shows the optimistic, pessimistic, and most likely estimates that the team has already made. 54. It is desirable to make an estimate that has a greater than 95% chance of being correct. Which of the following ranges of time for the impletion of the project best describes this probability of being correct?
In a project to install concrete sewer lines there is a lot of uncertainty as to how long the durations should be for the tasks involved. The project manager has determined that the team will use the PERT technique to evaluate the project’s completion date. The diagram shows nine activities and the table shows the optimistic, pessimistic, and most likely estimates that the team has already made. 55. What is the expected value of the duration for activity B?
In a project to install concrete sewer lines there is a lot of uncertainty as to how long the durations should be for the tasks involved. The project manager has determined that the team will use the PERT technique to evaluate the project’s completion date. The diagram shows nine activities and the table shows the optimistic, pessimistic, and most likely estimates that the team has already made. 56. What is the standard deviation for the duration of activity B?