PMP Questions

Multipel Choice Questions for PMP Examination Sämtliche Fragen und Bilder stammen aus der Website http://www.misterexam.com/pmp

Multipel Choice Questions for PMP Examination Sämtliche Fragen und Bilder stammen aus der Website http://www.misterexam.com/pmp

Anja Simons

Anja Simons

Set of flashcards Details

Flashcards 100
Students 24
Language English
Category Micro-Economics
Level Other
Created / Updated 12.08.2013 / 06.06.2025
Weblink
https://card2brain.ch/box/pmp_questions
Embed
<iframe src="https://card2brain.ch/box/pmp_questions/embed" width="780" height="150" scrolling="no" frameborder="0"></iframe>
81. Using the formula: Present value = S/(1+i)n where i is the interest rate in percentage, n isthe number of periods, and S is the starting amount, the following table is produced: Periods       10%            12%            14% 1                0.909      0.893      0.877 2                0.826      0.797      0.769 3                0.751      0.712      0.675 4                0.683      0.636      0.592 5                0.621      0.597      0.519 Based on the table, what is the value of an annual income flow of $1,300 each year overthe next three years at 12%?
82. Lifecycle costing:
A project manager is using the earned value reporting method to manage his project. Thefollowing table shows the data collected to date. The plan is for the project to be complete aftereight weeks. The earned value report shows data collected for the first four weeks of the project. The figure shown in the table are cumulative. Week       PV      AC      EV 1             1,000 1,000 1,000 2             3,000 2,000 2,500 3             5,000 5,000 6,000 4             7,000 9,000 7,000 5            13,000 6            17,000 7            19,000 8            20,000 83. What is the cost performance index for week 4?
A project manager is using the earned value reporting method to manage his project. Thefollowing table shows the data collected to date. The plan is for the project to be complete aftereight weeks. The earned value report shows data collected for the first four weeks of the project. The figure shown in the table are cumulative. Week       PV      AC      EV 1             1,000 1,000 1,000 2             3,000 2,000 2,500 3             5,000 5,000 6,000 4             7,000 9,000 7,000 5            13,000 6            17,000 7            19,000 8            20,000 84. What is the schedule performance index for week 3?
A project manager is using the earned value reporting method to manage his project. Thefollowing table shows the data collected to date. The plan is for the project to be complete aftereight weeks. The earned value report shows data collected for the first four weeks of the project. The figure shown in the table are cumulative. Week       PV      AC      EV 1             1,000 1,000 1,000 2             3,000 2,000 2,500 3             5,000 5,000 6,000 4             7,000 9,000 7,000 5            13,000 6            17,000 7            19,000 8            20,000 85. What is the BAC for the project during week 4?
A project manager is using the earned value reporting method to manage his project. Thefollowing table shows the data collected to date. The plan is for the project to be complete aftereight weeks. The earned value report shows data collected for the first four weeks of the project. The figure shown in the table are cumulative. Week       PV      AC      EV 1             1,000 1,000 1,000 2             3,000 2,000 2,500 3             5,000 5,000 6,000 4             7,000 9,000 7,000 5            13,000 6            17,000 7            19,000 8            20,000 86. During week 5 it is found that some of the work that was reported complete in week 2was considered unacceptable. It will require $500 to fix the problem and make this workacceptable. The work is scheduled to be done in week 6. No other work is reported to becomplete during week 5. What is the EV for week 5?
A project manager is using the earned value reporting method to manage his project. Thefollowing table shows the data collected to date. The plan is for the project to be complete aftereight weeks. The earned value report shows data collected for the first four weeks of the project. The figure shown in the table are cumulative. Week       PV      AC      EV 1             1,000 1,000 1,000 2             3,000 2,000 2,500 3             5,000 5,000 6,000 4             7,000 9,000 7,000 5            13,000 6            17,000 7            19,000 8            20,000 87. What is the cost variance for week 4?
A project manager is using the earned value reporting method to manage his project. Thefollowing table shows the data collected to date. The plan is for the project to be complete aftereight weeks. The earned value report shows data collected for the first four weeks of the project. The figure shown in the table are cumulative. Week       PV      AC      EV 1             1,000 1,000 1,000 2             3,000 2,000 2,500 3             5,000 5,000 6,000 4             7,000 9,000 7,000 5            13,000 6            17,000 7            19,000 8            20,000 88. What is the schedule variance in week 2?
A project manager is using the earned value reporting method to manage his project. Thefollowing table shows the data collected to date. The plan is for the project to be complete aftereight weeks. The earned value report shows data collected for the first four weeks of the project. The figure shown in the table are cumulative. Week       PV      AC      EV 1             1,000 1,000 1,000 2             3,000 2,000 2,500 3             5,000 5,000 6,000 4             7,000 9,000 7,000 5            13,000 6            17,000 7            19,000 8            20,000 89. What is the EAC at week 4?
90. The calculation of the EAC assumes that:
91. What factors need to be known in order to be able to calculate the ETC?
92. A construction company is being measured by the earned value reporting method.During the project one of the tasks, installing ten elm trees, was completed. The plannedvalue for this task was $4,000, and it was completed two weeks ago. Unfortunately forthe contractor, maple trees should have been planted. The customer insists that maple trees be planted and that the elm trees be removed. As of this time the elm trees are stillin the ground, but the contractor has agreed to do the work of replacing them. Whataction should be taken on the earned value report?
93. Learning curve theory emphasize that in producing many goods:
94. A project manager is considering applying learning curve theory to his project. Theproject involves designing a number of software modules that are very similar. Accordingto the cost figures that have been collected the first unit required 100 person-hours todesign and test. The second unit required 90 person-hours to design and test. Howmany person-hours will the eighth module take to design and test?
95. The process required to ensure that the project will satisfy the needs for which it wasundertaken include all activities of the overall management function that determines thequality policy, objectives, and responsibilities and implements them by means such asquality planning, quality control, quality assurance, and quality improvement, within thequality system. This is called:
96. Decisions as to the types of projects that should be accomplished and strategic plans asto the quality of the projects that are required should be the decision of which of thefollowing?
97. According to Deming and Juran most of the quality problems that exist are due to adefect or failure in processes that are controlled by:
98. A project manager is managing a large project and must consider the application of aquality management plan. One of the critical factors in such a plan is the cost ofimplementing the plan. The project manager should:
99. A project manager has discovered a problem and is trying to determine the cause. Theprocess whereby he identifies the variables that have the most influence on the projectby holding all the variables constant and changing one at a time is called:
100. A control chart is being used to control a manufacturing process. As part of the control asample of five parts is taken from the manufacturing process each hour of operation.Each of the five parts is measured and the dimension is recorded on the work sheet. Thedifference between the highest and lowest measured dimension of the five parts isplotted on the control chart. This is called which of the following values?