What's PRAM and what are the key features?

"Project Risk Analysis & Management"

-follows over the life cycle

-risk management strategy changes over the life cycle

What are the 4 main forms of a project termination?

-extinction (project is stopped; either successfull or not)

-addition (pm team = new operating group)

-integration (team back to normal organisation)

-starvation (politics, budget)

Why are closeouts difficult?

-sign off can be a de-motivator

-low priority activities

-unique view (not considering to transfer the learned issues)

-shortcuts on back-end

What are key reasons for an early termination?

-costs exceed business benefits

-not meeting the strategic criteria

-deadlines continued to be missed

-technological changes