The correct sequence of events in using Scrum framework is

Sprint Planning, Sprint, Daily Scrum, Sprint Review, and Sprint Retrospective

A _____________________ is created during the first half of the Sprint planning meeting
and a
_________________ is created during the second half of the Sprint planning meeting?

Sprint Backlog, collection of tasks

What should happen tp undefined or poorly defined Product Backlog item?

Undefined or poorly defined Product Backlog items should be kept out from the Product Backlog until sufficient detail is known

What is the recommended size for a Development Team?

6, +3 or -3

The Product Backlog is maintained by the:

Product Owner

Who is on the Scrum Team?

  • Product Owner
  • Development Team
  • Scrum Master

What does it mean for an activity to be time-boxed?

There is a maximum time limit for the activity

What might the Scrum Team discuss during a Sprint Retrospective?

  • Methods of communication
  • The way the Scrum Team does Sprint Planning
  • Skills needed to improve the Development Team's ability to deliver
  • Its Definition of Done

Is Scrum an implementation of Agile Development?

Yes

Who should know the most about the progress toward a business objective or a release,
and be able to explainthe alternatives most clearly?

The product owner

More than one Scrum Team is working on a single project or release. How should the
Product Backlog bearranged?

All Scrum Teams work from a common Product Backlog and integrate their work every sprint

Who is required to attend the Daily Scrum?

Development Team

The Sprint Backlog is owned by?

The Development Team

According to Scrum, the amount of time for a team to plan Sprint activities is expressed in
what unit of time?

Hours

When is the Sprint Backlog created?

Prior to the Sprint Planning meeting

What is the maximum time that Scrum recommends the team spend in the daily scrum (daily standup)?

Fifteen minutes

When many Scrum Teams are working on a project, what best describes the definition of "done"?

All teams must use the same definition

What is not reflected in a Sprint Burndown Chart?

  • Total Days in Sprint
  • Day of Sprint
  • Work Hours Remaining

Who defines the Sprint Backlog scope?

Development Team

Who determines whether the development team has been assigned enough work in a Sprint?

The Development Team

Which objectives are covered as part of Sprint Planning?

Understanding what functionality the Product Owner desires within the next Sprint and figuring out how to doit.

Upon what type of process control is Scrum based?

Empirical

You are the Scrum Master and the very first Sprint will complete in 5 days. You are creating
a meeting invite forthe Sprint Review to demo the items completed in the Sprint. Who
should you invite as a required attendee to the Sprint Review?
 

  • Product Owner(s)
  • Development Team

When should the Product Owner ship or implement a Sprint increment?

When it makes sense

How could the team and other stakeholders know if a product backlog item is done?

Ask to the Product Owner

What is the primary responsibility of the Scrum Master?

To remove any impediments the Development Team encounters during their work

Which of the following is not a Product Owner responsibility?

Assigning tasks to team members

How many hours per day should a person on a Scrum team work?

A sustainable pace, usually from 7-8 hours per day.

What are the roles in the Scrum framework?

  • Development Team
  • Product owner
  • Scrum Master

What artifact shows actual versus planned progress?

Burndown Chart

What may a Development Team deliver at the end of a Sprint?

  • A single document, if that is what the Product Owner asked for
  • An increment of working software that is "done."

Is the product owner responsible for running the daily scrum meeting?

No

The Sprint Goal is selected before the Sprint Backlog is created.

True

Under what circumstances should the Product Backlog be reprioritized?

The Product Owner should reprioritize the Product Backlog whenever new information is learned

What is the maximum amount of time a sprint retrospective should take?

3 hours, for an 30 days Sprint

The Development Team should have all the skills needed to:

Turn the Product Backlog it selects into an increment of potentially shippable product functionality.

Is Scrum Master a "management" position?

Yes

As the Sprint planning progresses, the workload has grown beyond the development team's capacity. Which action makes most sense for the Team?

Collaborate with the Product Owner and potentially remove or change items

Which of the following is reflected in a Sprint Burndown Chart?

Work Hours Remaining

Do Development Team members volunteer to own a Sprint Backlog item?
 

Never. All Sprint Backlog Items are "owned" by the entire Development Team, even though each one maybe done by an individual team member