This flashcard set delves into the intricacies of project management, focusing on key concepts like work breakdown structures, cost management, and schedule performance. It covers essential terms such as earned value, planned value, and various contract types, providing a comprehensive overview of project management techniques and methodologies. Ideal for project managers and professionals aiming to achieve PMP certification, this flashcard set offers a structured approach to understanding and applying project management principles effectively.
Flashcards
95
Students
10
Language
English
Category
Micro-Economics
Level
Other
Created / Updated
09.05.2013 / 04.11.2025

Lernkarten

Project Manager (PM)

The person assigned by the performing organization to achieve the project objectives.. . . . .

Request for Information (RFI)

A type of procurement document whereby the buyer requests a potential seller to provide various pieces of information related to a product or service or seller capability.. . . . .

Request for Proposal (RFP)

A type of procurement document used to request proposals from prospective sellers of products or services. In some application areas, it may have a narrower or more specific meaning.. . . .

Request for Quotation (RFQ)

A type of procurement document used to request price quotations from prospective sellers of common or standard products or services. Sometimes used in place of request for proposal and in some application areas, it may have a narrower or more specific meaning.. . . .

Schedule Performance Index (SPI)

A measure of schedule efficiency on a project. It is the ratio of earned value (EV) to planned value (PV). The SPI = EV divided by PV.. . .

Schedule Variance (SV)

A measure of schedule performance on a project. It is the difference between the earned value (EV) and the planned value (PV). SV = EV minus PV.. . .

Scheduled Finish Date (SF)

The point in time that work was scheduled to finish on a schedule activity. The scheduled finish date is normally within the range of dates delimited by the early finish date and the late finish date. It may reflect resource leveling of scarce resources. Sometimes called planned finish date.. .

Scheduled Start Date (SS)

The point in time that work was scheduled to start on a schedule activity. The scheduled start date is normally within the range of dates delimited by the early start date and the late start date. It may reflect resource leveling of scarce resources. Sometimes called planned start date.. .

Start-to-Finish (SF)

The logical relationship where completion of the successor schedule activity is dependent upon the initiation of the predecessor schedule activity. See also logical relationship.. . . .

Start-to-Start (SS)

The logical relationship where initiation of the work of the successor schedule activity depends upon the initiation of the work of the predecessor schedule activity. See also logical relationship.. . . .

Statement of Work (SOW)

A narrative description of products, services, or results to be supplied.. . . . .

To-Complete-Performance-Index (TCPI)

The calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal, such as the budget at completion (BAC) or the estimate at completion (EAC). It is the ratio of "remaining work" to the "funds remaining". . . .

OPM3

Organizational Project Management Maturity Model

MBO

Management By Objectives

Present Value (PV) =

   FV   
 (1+r)n
 

FV=Future Value
r=interest rate
n=number of time periods

Achtung: zu verwechseln mit PV Planned Value 