PMP Zertifizierung - Glossar

PMP Zertifizierung - Glossar

PMP Zertifizierung - Glossar


A. O.
This flashcard set delves into the intricacies of project management, focusing on key concepts like work breakdown structures, cost management, and schedule performance. It covers essential terms such as earned value, planned value, and various contract types, providing a comprehensive overview of project management techniques and methodologies. Ideal for project managers and professionals aiming to achieve PMP certification, this flashcard set offers a structured approach to understanding and applying project management principles effectively.
Karten
95
Lernende
10
Sprache
Englisch
Kategorie
BWL
Stufe
Andere
Erstellt / Aktualisiert
09.05.2013 / 04.11.2025

Lernkarten

RAM

responsibility assignment matrix

RBS

risk breakdown structure

RFI

request for information

RFP

request for proposal

RFQ

request for quotation

SF

start-to-finish

SOW

statement of work

SPI

schedule performance index

SS

start-to-start

SV

schedule variance

SWOT

strengths, weaknesses, opportunities, and threats

T&M

time and material

TQM

Total Quality Management

WBS

work breakdown structure

Actual Cost (AC)

Total costs actually incurred and recorded in accomplishing work performed during a given time period for a schedule activity or work breakdown structure component. Actual cost can sometimes be direct labor hours alone, direct costs alone, or all costs including indirect costs. Also referred to as the actual cost of work performed (ACWP). See also earned value management and earned value technique.. .

Budget at Completion (BAC)

The sum of all the budgets established for the work to be performed on a project or a work breakdown structure component or a schedule activity. The total planned value for the project.. . . .

Change Control Board (CCB)

A formally constituted group of stakeholders responsible for reviewing, evaluating, approving, delaying, or rejecting changes to a project, with all decisions and recommendations being recorded.. . . . .

Cost Performance Index (CPI)

A measure of cost efficiency on a project. It is the ratio of earned value (EV) to actual costs (AC). CPI = EV divided by AC.. . .

Cost Variance (CV)

A measure of cost performance on a project. It is the difference between earned value (EV) and actual cost (AC). CV = EV minus AC.. . .

Cost-Plus-Fixed-Fee (CPFF) Contract

A type of cost-reimbursable contract where the buyer reimburses the seller for the seller's allowable costs (allowable costs are defined by the contract) plus a fixed amount of profit (fee).. . . . .

Cost-Plus-Incentive-Fee (CPIF) Contract

A type of cost-reimbursable contract where the buyer reimburses the seller for the seller's allowable costs (allowable costs are defined by the contract), and the seller earns its profit if it meets defined performance criteria.. . . . .

Duration (DU or DUR)

The total number of work periods (not including holidays or other nonworking periods) required to complete a schedule activity or work breakdown structure component. Usually expressed as workdays or workweeks. Sometimes incorrectly equated with elapsed time. Contrast with effort.. .

Early Finish Date (EF)

In the critical path method, the earliest possible point in time on which the uncompleted portions of a schedule activity (or the project) can finish, based on the schedule network logic, the data date, and any schedule constraints. Early finish dates can change as the project progresses and as changes are made to the project management plan.. . . .

Early Start Date (ES)

In the critical path method, the earliest possible point in time on which the uncompleted portions of a schedule activity (or the project) can start, based on the schedule network logic, the data date, and any schedule constraints. Early start dates can change as the project progresses and as changes are made to the project management plan.. . . .

Earned Value (EV)

The value of work performed expressed in terms of the approved budget assigned to that work for a schedule activity or work breakdown structure component. Also referred to as the budgeted cost of work performed (BCWP).. . . .

Earned Value Management (EVM)

A management methodology for integrating scope, schedule, and resources, and for objectively measuring project performance and progress. Performance is measured by determining the budgeted cost of work performed (i.e., earned value) and comparing it to the actual cost of work performed (i.e., actual cost).. . . .

Earned Value Technique (EVT) [Technique]

A specific technique for measuring the performance of work and used to establish the performance measurement baseline (PMB).. . . . .

Estimate at Completion (EAC) [Output/Input]

The expected total cost of a schedule activity, a work breakdown structure component, or the project when the defined scope of work will be completed. The EAC may be calculated based on performance to date or estimated by the project team based on other factors, in which case it is often referred to as the latest revised estimate. See also earned value technique and estimate to complete.. . .

Estimate to Complete (ETC) [Output/Input]

The expected cost needed to complete all the remaining work for a schedule activity, work breakdown structure component, or the project. See also earned value technique and estimate at completion.. . . .

Expected Monetary Value (EMV) Analysis

A statistical technique that calculates the average outcome when the future includes scenarios that may or may not happen. A common use of this technique is within decision tree analysis.. . . .

Finish-to-Finish (FF)

The logical relationship where completion of work of the successor activity cannot finish until the completion of work of the predecessor activity. See also logical relationship.. . . .

Finish-to-Start (FS)

The logical relationship where initiation of work of the successor activity depends upon the completion of work of the predecessor activity. See also logical relationship.. . . .

Firm-Fixed-Price (FFP) Contract

A type of fixed price contract where the buyer pays the seller a set amount (as defined by the contract), regardless of the seller's costs.. . . . .

Fixed-Price-Incentive-Fee (FPIF) Contract

A type of contract where the buyer pays the seller a set amount (as defined by the contract), and the seller can earn an additional amount if the seller meets defined performance criteria.. . . . .

Invitation for Bid (IFB)

Generally, this term is equivalent to request for proposal. However, in some application areas, it may have a narrower or more specific meaning.. . . .

Late Finish Date (LF)

In the critical path method, the latest possible point in time that a schedule activity may be completed based upon the schedule network logic, the project completion date, and any constraints assigned to the schedule activities without violating a schedule constraint or delaying the project completion date. The late finish dates are determined during the backward pass calculation of the project schedule network.. . . .

Late Start Date (LS)

In the critical path method, the latest possible point in time that a schedule activity may begin based upon the schedule network logic, the project completion date, and any constraints assigned to the schedule activities without violating a schedule constraint or delaying the project completion date. The late start dates are determined during the backward pass calculation of the project schedule network.. . . .

Planned Value (PV)

The authorized budget assigned to the scheduled work to be accomplished for a schedule activity or work breakdown structure component. Also referred to as the budgeted cost of work scheduled (BCWS).. . . .

Program Evaluation and Review Technique (PERT)

A technique for estimating that applies a weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.. . . . .

Project Management Office (PMO)

An organizational body or entity assigned various responsibilities related to the centralized and coordinated management of those projects under its domain. The responsibilities of a PMO can range from providing project management support functions to actually being responsible for the direct management of a project.. . . .