PMI - Project Integration Management
Flashcards to help remember the processes for PMI Project Integration Management
Flashcards to help remember the processes for PMI Project Integration Management
-
- 1 / 19
-
Lernkarten
What are the Tools and Techniques for the Direct and Manage Process Work Process?
- Expert Judgement
- PMIS
- Meetings
What are the outputs of the Direct and Manage Project Work process?
- Deliverables
- Change Requests
- Work Performance Data
- Project Mananagement Plan updates
- Project Document updates
What are the inputs to Monitor and Control Project Work?
- Project Management Plan
- Schedule Forecast
- Cost Forecast
- Validated Changes
- Work Performance Information
- EEFs
- OPAs
What are the tools and techniques for Monitor and Control Project work?
- Expert Judgement
- PMIS
- Analytical Techniques
- Meetings
What are the outputs to the Monitor and Control Project Work process?
- Change Requests
- Work Performance Reports
- Project Management Plan updates
- Project documentation updates
What are the inputs to the Perform Integrated Change Control?
- Project Manangement Plan
- Change Requests
- Work Performance Reports
- OPAs
- EEFs
What are the tools and techniques for Perform Integrated Change Control process?
- Expert Judgement
- Meetings
- Change Control Tools
Whata re the outputs of the Perform Integrated Change Control Process?
- Approved Change Requests
- Change Log
- Project Management Plan updates
- Project documentation updates
What are the inputs to the Close Project or Phase process?
- Project Management Plan
- Accepted deliverables
- OPAs
What are the Tools and Techniques for Close Project or Phase Process
- Expert Judgement
- Meetings
- Analytical Techniques
What are the outputs of the Close Project or Phase process?
- The completed product,service or result transition
- OPA updates