PMI - Project Integration Management
Flashcards to help remember the processes for PMI Project Integration Management
Flashcards to help remember the processes for PMI Project Integration Management
Set of flashcards Details
Flashcards | 19 |
---|---|
Language | English |
Category | Computer Science |
Level | Primary School |
Created / Updated | 17.09.2013 / 23.12.2019 |
Licencing | No Copyright (CC0) |
Weblink |
https://card2brain.ch/box/pmi_project_integration_management
|
Embed |
<iframe src="https://card2brain.ch/box/pmi_project_integration_management/embed" width="780" height="150" scrolling="no" frameborder="0"></iframe>
|
What are the processes of Project Integration and their phases?
- Develop Project Charter (Initiate)
- Develop Project Management Plan(Plan)
- Direct & Manage Project Work(Execute)
- Monitor & Control Procevt Work(M&C)
- Perform Integrated Change Control(M&C)
- Close Project or Phase(Close)
What are the inputs of the Develop Project Charter Process
- Project Statement of Work
- Business Case
- Agreements
- EEFs
- OPAs
What are the tools and techniques of the Develop Project Charter Process?
- Expert Judgement
- Faciliatation Techniques
What are the outputs of the Develop Project Charter Process
Project Charter
What are the inputs of the Develop Project Management Plan?
- Project Charter
- Outputs from other processes
- OPAs
- EEFs
What are the tools and techniques for the Develop Project Management Plan process?
- Expert Judgement
- Facilitation Techniques
What are the outputs of Develop Project Management Plan Process?
Project Management Plan
What are the inputs of the Direct and Manage Project Work Process?
- Project Management Plan
- Approved Change Requests
- OPAs
- EEFs