What's PRAM and what are the key features?
"Project Risk Analysis & Management"
-follows over the life cycle
-risk management strategy changes over the life cycle
What are the 4 main forms of a project termination?
-extinction (project is stopped; either successfull or not)
-addition (pm team = new operating group)
-integration (team back to normal organisation)
-starvation (politics, budget)
Why are closeouts difficult?
-sign off can be a de-motivator
-low priority activities
-unique view (not considering to transfer the learned issues)
-shortcuts on back-end
What are key reasons for an early termination?
-costs exceed business benefits
-not meeting the strategic criteria
-deadlines continued to be missed
-technological changes