65. Tom is the project manager on a construction project. Midway through his project, he realizes that thereÍs a problem with the lumber theyÍve been using in a few rooms and theyÍre going to have to tear down some of the work theyÍve done and rebuild. One of his team members suggests that the defect isnÍt bad enough to cause all of that re-work. Tom says that heÍs worked on a project that made this same mistake before and they ended up having to redo the work when inspectors looked at the house. He convinces the team member that itÍs probably better to fix it now than later. What kind of power is he using to make the decision?
66. Which of the following is NOT one of the most common sources of project conflict?
63. You are developing the project charter for a new project. Which of the following is NOT part of the enterprise environmental factors?
64. You are managing a construction project to install new door frames in an office building. You planned on spending $12,500 on the project, but your costs are higher than expected, and now youÍre afraid that your project is spending too much money. What number tells you the difference between the amount of money you planned on spending and what youÍve actually spent so far on the project?
74. You are managing a software engineering project, when two team members come to you with a conflict. The lead developer has identified an important project risk: you have a subcontractor that may not deliver on time. Another developer doesnÍt believe that the risk is likely to happen
75. Which of the following BEST describes the contents of a WBS Dictionary entry?
112. You are conducting a status meeting and monitoring your risk register when you discover a risk that remains even after you implement all of your response strategies. What kind of risk is this and what should you do about it?
103. You are managing a software engineering project, when two team members come to you with a conflict. The lead developer has identified an important project risk: you have a subcontractor that may not deliver on time. Another developer doesnÍt believe that the risk is likely to happen