.
-
- 1 / 154
-
Flashcards
155. A project manager on a construction project includes a line item in the budget for insurance for the equipment and job site. This is an example of:
156. You are talking to experts and gathering independent estimates for your contract. Which of the following BEST describes what you are doing?
153. Which of the following contracts has the MOST risk for the seller?
154. You are managing an industrial design project for an important client. Two of your team members have a disagreement on project priorities. One person wants to do certain activities first, while the other feels they should be left until the end of the project. You work with both people to forge a compromise where those activities are neither first nor last, but instead done in the middle of the project. Nobody is particularly unhappy with this solution. Another name for a compromise is a:
157. A project manager is creating a report of the final status of a closed project to the stakeholders. Which of the following is NOT used in a final project report to communicate the status of a project?
147. Which of the following is NOT true about the Project Charter?
148. YouÍre managing a construction project to install several hundred air conditioner panels in a new office building. Every floor has identical panels. The customer, a construction contracting company, has provided specifications for the installations. The team is using a process to install and verify each panel. As the team completes each panel, your teamÍs quality control inspector measures it and identifies defects. The root cause of each defect is identified. You want to identify the ongoing trends of defective installations. Which is the BEST tool to use for this?
145. A member of your seven-person project team comes up with a controversial idea. Two others agree that it should be pursued. Two members of the team are opposed to it, while the remaining two have a different approach. You end up going with the controversial idea. This is an example of:
151. There have been several rounds of layoffs at your company. Now your project team is worried about their job security, and youÍve noticed that their performance has decreased significantly because of it. This is predicted by which motivational theory?
152. Which of the following is NOT included in a cost of quality calculation?
150. You are a project manager for a software project. As you are defining the scope of the work you need to do, you sit down with all of the projectÍs stakeholders and record all of the requirements you can get from them. Which of the following is NOT a valid requirement from stakeholder analysis?
139. YouÍre managing a project that is currently executing. YouÍre evaluating the work being performed by constantly measuring the project performance, and recommending changes, repairs, and corrections where necessary. What process are you performing?
144. Which of the following describes the contents of a staffing management plan?
143. Joe is an excellent programmer. He was promoted to a role of Project Manager because he understands technology better than anyone else in the company. Unfortunately, he is having trouble doing the project management job and his projects are failing. What is this an example of?
186. A project manager is faced with two team members who have conflicting opinions. One team member explains her side of the conflict, and presents a possible solution. But before the other team member starts to explain his side of things, the project manager says, ñIÍve heard enough, and IÍve decided to go with the solution IÍve heard.î This is an example of:
187. As you determine the requirements, constraints, and assumptions for the project you record them in which document?
188. YouÍve been hired by a large consulting firm to evaluate a software project for them. You have access to the CPI and EV for the project, but not the AC. The CPI is .92, and the EV is $172,500. How much money has actually been spent on the project?
189. Approved changes are implemented in which process?