Diese Karteikarten behandeln fortgeschrittene Themen des Projektmanagements auf Universitätsniveau, mit Fokus auf Projektcharter, Risikomanagement, Stakeholder-Kommunikation und Konfliktlösung. Sie eignen sich für Studierende und Berufstätige, die ihr Wissen in Projektmanagement vertiefen möchten, insbesondere in den Bereichen Bau- und Softwareprojekte. Die Karteikarten decken auch Themen wie die Identifizierung von Risiken, die Verwaltung von Projektverträgen und die Anwendung von Tools wie Ishikawa-Diagrammen ab.
Karten
154
Lernende
3
Sprache
Deutsch
Kategorie
Informatik
Stufe
Universität
Erstellt / Aktualisiert
05.01.2014 / 28.05.2015

Lernkarten

190. YouÍve been hired by a large consulting firm to lead an accounting project. You determine the needs of the project and divide the work up into work packages so that you can show how all of it fits into categories. What are you creating?

191. Over half of conflicts on projects are caused by:

192. Which of the following is NOT a tool or technique of Monitor and Control Risks?

193. You work for a consulting company and your team has implemented an approved scope change on your project. You need to inform your client that the change has been made. WhatÍs the best form of communication to use for this?

178. You are the project manger of a software project. Two developers, Bill and Alfredo, are having an argument about how to implement a feature. Bill thinks that itÍs more important that the project get done quickly, so heÍs suggesting that you re-use some work thatÍs been done on a previous project to get started. Alfredo thinks that that work doesnÍt apply to this project and will just waste time. Bill is almost always right about these things and heÍs very influential on the team, so itÍs important that you keep him happy. What should you do?

179. Which of the following is NOT an example of a deliverable?

180. Which is NOT an input to the Create WBS process?

181. Which of the following is the correct order of actions that you take during the Closing processes?

182. At the beginning of the project, you hold a meeting with all of the stakeholders in your project in order to figure out how everyone will communicate as the work goes on. Which of the following terms best describes that meeting?

183. You are managing a project with 23 team members and 6 key stakeholders. Two team members identify a problem with the current approach. Addressing that problem will require changes to the project plan and its subsidiary plans. One of the stakeholders previously indicated that any delays are unacceptable, and your team members tell you that itÍs possible the change could cause the team to miss at least one critical deadline. What is the BEST way to deal with this situation?

184. You have been asked to select between three projects. Project A has a net present value of $54,750 and will take six months to complete. Project B has a net present value of $85,100 and will take two years to complete. Project C has a net present value of $15,000 and a benefit- cost ratio of 5:2. Which project should you choose?

185. Which of the following is a defect?

170. Which of the following are valid ways to breakdown the work in a WBS?
169. Which of the following is NOT part of the Close Project or Phase process?

173. Which of the following tools is used to document the lessons that were learned when the contract was administered?

171. Which of the following is an output of Direct and Manage Project Execution?

175. A project manager is running into problems with the team. People are repeatedly running into trouble over seemingly small problems: who takes notes at meetings, what dress is appropriate for the office, who people need to notify when they take a day off. The problems started out small, but as more people run into more problems the situation is rapidly escalating. This situation is most likely caused by a lack of:

174. You are managing a project to build a new wing onto a local school building over a summer break. One night, the school and your construction site are destroyed by a tornado. Your client demands that you continue work despite the disaster, but you consult the contract, and find a clause that states that you are not responsible for any more work. This is referred to as:

177. Which of the following is NOT an output of Monitor & Control Project Work?

176. Which of the following BEST describes when you perform the Monitor and Control Project Work process?

162. Mike is a project manager for an IT technology implementation project. He is using an Ishikawa diagram to figure out what could cause potential risks on his project. Which process is he doing?
161. Your project has a virtual team. Half of your team members are located in another country, where they are working for a subcontractor. The subcontractorÍs team members speak a different dialect of English than your team does. After a conference call, two of your team members make jokes about the way your subcontractorÍs team members speak. What is the BEST way to handle this situation?
164. YouÍre holding a PMP training seminar for people in your company to help them obtain enough hours to qualify to take the PMP exam. This is an example of:
163. Amit is the manager of a software project. His client has agreed on a Project Scope Statement at the beginning of the project, but whenever the client verifies deliverables, he comes up with features that he would like to add into the product. Amit is working with the client to find what requirements were missed in the planning stages of the project and how to plan better in the future. What is the BEST description of his projectÍs current situation?
166. You are working with potential sponsors to determine which project your company will pursue. Based on the benefit-to-cost (BCR) ratios, which of the following four projects should you recommend?
165. You are managing a construction project to install wiring in an office building. You discover that one of your team members has taken a box of cable from the job site so he can wire his attic. What is the BEST way to respond?
168. YouÍre managing a software project. Your team has discovered a problem, and as a result youÍve requested a change. The change will cost the project an extra three weeks, but without it several stakeholders might have problems with the final product. WhatÍs the NEXT thing that you should do?

167. What are the 5 kinds of power?

199. You are managing a large construction project thatÍs been broken down into subprojects (or phases). Each of these subprojects is scheduled to take between three and six months to complete. At the end of each sub- project, you plan to go through the closing processes and document lessons learned. Which of the following BEST describes what you must do at the beginning of each subproject or phase?

198. A project manager discovers that a project problem has occurred. The problem was never discussed during risk planning activities or added to the risk register, and it will now cost the project money. What is the BEST response?

197. Your project just completed, and one of your subcontractors has sent you floor seats to the next big hockey game to thank you for your business. What is the BEST way to respond?

196. In which process do you create the Risk Breakdown Structure?

195. What are the strategies for dealing with positive risks?

194. Which of the following is NOT typically found in a project charter?