16. YouÕre managing a project to build a new project management information system. You work with the team to come up with an estimate of 27 weeks. In the best case, this could be shortened by two weeks because you can reuse a previous component. But thereÕs a risk that a vendor delay could cause the project to be delayed by five weeks. Use PERT to calculate a three-point estimate for this project.
2. YouÕre working on a project that has an EV of $7362 and a PV (BCWS) of $8232. WhatÕs your SV?
5. Your company has two projects to choose from. Project A is a billing software project for the Accounts payable department; in the end it will make the company around $400,000 when it has been rolled outto all of the employees in that department. Project B is a payroll application that will make the company around $388,000 when it has been put to use throughout the company. After a long deliberation, your board chooses to go ahead with Project B. What is the opportunity cost for choosing Project B over Project A?