52. You are managing a construction project that is currently being initiated. You met with the sponsors, and have started to work on identifying stakeholders. YouÕve documented several key stakeholders and identified their needs. Before you can finish initiating the project, your company guidelines require that you make a rough order of magnitude estimate of both time and cost, so that the sponsor can allocate the final budget. WhatÕs the range of a rough order of magnitude (ROM) estimate?
51. The scope baseline consists of:
54. Mary is a project manager at a consulting company. The company regularly builds teams to create products for clients. When the product is delivered, the team is dissolved and assigned to other projects. What kind of organization is she working for?
53. Which of the following processes is in the Initiating process group?
56. At the close of your project, you measure the customer satisfaction and find that some customer needs were not fully met. Your supervisor asks you what steps you took on your project to improve customer satisfaction. Which subsidiary plan would you consult to determine this information?
57. Customer satisfaction should be measured at the end of the project to maintain long-term relationships. Which of the following is NOT always an aspect of customer satisfaction?
55. An important part of performing stakeholder analysis is documenting quantifiable expectations. Which of the following expectations is quantifiable?