Diese Vokabelkartei für German an der Universität umfasst 153 Karteikarten mit Multiple-Choice-Fragen zu Projektmanagement, Risikomanagement und Teamführung. Sie konzentriert sich auf Fachbegriffe wie "Schedule Performance Index (SPI)", "Cost Performance Index (CPI)" und "Earned Value (EV)", sowie auf Prozesse wie "Close Project or Phase" und "Control Risks". Die Plattform unterstützt auch das Rückwärtslernen von der Zielsprache zur Ausgangssprache, was sie ideal für fortgeschrittene Lerner macht, die ihre Kenntnisse vertiefen möchten.
Cartes-fiches
153
Utilisateurs
5
Langue
Allemand
Catégorie
Allemand
Niveau
Université
Créé / Mis à jour
28.10.2019 / 07.11.2019

Cartes-fiches

Which of the following statements regarding the process "Develop Schedule" is not correct?

Which type of cost is team training?

A project has two critical paths. Which of the following BEST describes how this affects the project? 

An activity has an early start (ES) of day 1, a late start (LS) of day 5, an early finish (EF) of day 10 and a late finish (LF) of day 14. The activity:

Rearranging resources so that a constant number of resources is used each month is called?

Which of the following statements is right? 

Cause-and-effect diagrams are also called?

A product meets the customer's requirements. What does this mean? 

Which of the following is no valid technique for Quality Management? 

Extensive use of ____ communication is most likely to aid in solving complex problems

A project manager on a multinational Web site implementation project is at a party and talks to friends who will be heavy users of this new Web site when the project is complete and the site is rolled out. They describe some annoying aspects of the current Web site. The project manager takes the feedback back to the sponsor and encourages design and scope changes. Which of the following BEST describes what the project manager has done?

During project planning in a matrix organization, the project manager determines that additional human resources are needed. From whom would he request these resources?

The pareto principle states that ____ percent of the problems are due to 20 percent of the root causes

Which of the following is not a valid organizational structure?

Who is ultimately responsible for quality management on the project? 

Which of the following is done by the project manager?

All of the following are ALWAYS inputs to the risk management process EXCEPT: 

A team member is not performing well on the project because she is inexperienced in system development work. There is no one else available who is better qualified to do the work. What is the BEST solution for the project manager?

An organization is going through an evolutionary phase of restructuring the way it does projects. In a shift from a strong matrix organization to a weak matrix organization, the power is shifted from the: 

What is the number of communication channels if there are 5 participants in a meeting? 

With which type of contract is the buyer least concerned about project costs?

Which one of the following is NOT a response strategy for negative risks or threats?

Which of the following activities doesn't occur during the Plan Procurements process?

Which Statement about quality audits is correct? 

Outputs of the Plan Risk Responses process include

Which of the following can not be found in a decision tree?

Which of the following is a control tool for Quality Management? 

Which of the following is not a contract type category?

If you ask the client to handle some of the work which type of risk response is this?

What is an Output of process 'Manage Project Knowledge'?

All of the following result from quality audits EXCEPT

Which of the following Statements regarding this decision tree is correct?

Which of the following explains why quality is planned in and not inspected in?

If you mitigate a negative risk, you reduce ...

Which of the following risks is the biggest threat to the project?

If you ask the client to handle some of the work which type of risk response is this?

With which type of contract is the buyer least concerned about project costs? 

If you mitigate a negative risk, you reduce ...

Which of the following statements regarding this decision tree is not correct?

Secondary risks are 