Diese Lernkarten decken fortgeschrittene Themen der Projektmanagement-Methodik ab, wie sie an Universitäten gelehrt wird. Sie konzentrieren sich auf Schlüsselkonzepte wie Kommunikation, Kostenmanagement, Qualitätskontrolle und Risikomanagement, wobei Techniken wie die Delphi-Methode und die Pareto-Prinzipien im Mittelpunkt stehen. Projektmanager und Studierende der Informatik profitieren von diesen Karteikarten, da sie praktische Einblicke in die Planung und Steuerung von Projekten bieten, einschließlich der Nutzung von Verantwortungsmatrizen und der Bewältigung von Organisationsstrukturen.
Cartes-fiches
77
Utilisateurs
27
Langue
Allemand
Catégorie
Informatique
Niveau
Université
Créé / Mis à jour
26.10.2019 / 13.01.2021

Cartes-fiches

Which of the following processes includes asking teammembers about the time
estimates for their activities?

Which of the following is NOT needed in order to come up with a project estimate?

Which of the following is CORRECT?

Which of the following is a chief characteristic of the Delphi technique?

Which of the following is not a valid organizational structure?

Which of the following is no valid technique for Quality Management?

Which of the following is NOT done by the project sponsor?

Which of the following statements is wrong?

Which of the following can not be found in a control chart?

Which of the following is NOT needed in order to come up with a project estimate?
Select one:

Which one of the following PMI processes is executed directly after the Plan Cost
Management process?

Which one of the following PMI processes is directly followed by the Develop Schedule
process?

Which one of the following PMI processes is directly followed by the Estimate Activity
Resources process?

Which of the following processes includes asking teammembers about the time estimates for
their activities?

Which of the following is no valid technique for Quality Management?

Which of the following is NOT done by the project sponsor?

Which of the following is a chief characteristic of the Delphi technique?

Which of the following statements is wrong?

All of the following are common results of risk management EXCEPT:

Which of the following can not be found in a control chart?

A team member from research and development tells you that her work is too creative to provide you with a fixed single estimate for
the activity. You both decide to use the labor hours per installation from past projects to predict the future. This is an example of
which of the following ?

Which of the following is NOT needed in order to come up with a project estimate?

Which of the following statements regarding the process "Develop Schedule" is not correct?

Which type of cost is team training?

A project has two critical paths. Which of the following BEST describes how this affects the project?

An activity has an early start (ES) of day 1, a late start (LS) of day 5, an early finish (EF) of day 10 and a late finish (LF) of day 14.
The activity:

Which of the following statements is right?

Cause-and-effect diagrams are also called?

A product meets the customer's requirements. What does this mean?

Which of the following is no valid technique for Quality Management?

The pareto principle states that ____ percent of the problems are due to 20 percent of the root causes

Which of the following is not a valid organizational structure?

Who is ultimately responsible for quality management on the project?

Which of the following is done by the project manager?

All of the following are ALWAYS inputs to the risk management process EXCEPT:

An organization is going through an evolutionary phase of restructuring the way it does projects. In a shift from a strong matrix
organization to a weak matrix organization, the power is shifted from the:

What is the number of communication channels if there are 5 participants in a meeting?