Project Management for Construction Projects

ETHZ / HS2022 / Bauingenieurwissenschaften Master / Project Management for Construction ProjectsWith this and the kahoot multiple choice questions you're good to go! 5.0 guaranteed!

ETHZ / HS2022 / Bauingenieurwissenschaften Master / Project Management for Construction ProjectsWith this and the kahoot multiple choice questions you're good to go! 5.0 guaranteed!


D. B.
This flashcard set covers advanced project management techniques for construction projects at the university level. It focuses on key concepts like cost estimation, risk management, scheduling, and various delivery methods, including critical path analysis, lean scheduling, and different types of contracts. The flashcards delve into topics such as cost performance indices, resource management, and the bidding process, providing valuable insights for students and professionals in the construction industry. The set includes numerous examples and explanations, making it a comprehensive resource for understanding the complexities of managing construction projects efficiently.
Karten
94
Lernende
1
Sprache
Englisch
Kategorie
BWL
Stufe
Universität
Erstellt / Aktualisiert
24.11.2022 / 28.12.2022

Lernkarten

Near miss

Potential for loss but none occurred

The safety cultural change journey

Safety measures during construction

Safety monitoring with AI - Value

Reduce on-site security

Replace checklists

reduce workplace injuries

provide a safe environment

access control of restricted areas

Behavior-Based Safety Improvement Model

Reactive Safety Management

Active Safety Management

Critical Path

The of longest sequence activities that must be finished on time in order for the project to be complete.

SPI

Schedule Perfoming Index

Measure of schedule efficiency on a project.

SPI = BCWP / BCWS = EV / PV

SPI > 1 --> good (ahead of schedule)
SPI < 1 --> bad (behind schedule)

CPI

Cost Performance Index

CPI = BCWP / ACWP = EA / AC

A metric from the EVA method.

CPI

Cost performance index

Measure of cost efficiency on a project.

CPI = BCWP / ACWP = EV / AC

CPI > 1 --> good (below budget)
CPI < 1 --> bad (over budget)

BCWS

budgeted cost of work scheduled

a.k.a. planned value (PV)

BCWS = total cost * %planned work

ACWP

actual cost of work performed

a.k.a. actual cost (AC)

ACWP = what is paid for an activity

BCWP

budgeted cost of work performed

a.k.a. earned value (EV)

BCWP = total cost * %work done

Lernen