V02 Service Provision

- Service model as guiding principles of the design and building process

- Service model as guiding principles of the design and building process


Set of flashcards Details

Flashcards 15
Language Deutsch
Category Career Studies
Level University
Created / Updated 07.01.2020 / 28.01.2020
Licencing Not defined
Weblink
https://card2brain.ch/box/20200107_v02_service_provision
Embed
<iframe src="https://card2brain.ch/box/20200107_v02_service_provision/embed" width="780" height="150" scrolling="no" frameborder="0"></iframe>

What are the two duties of consultants according to SIA? What is the big difference between the service of a consultant and a service of work?

  • Duty of loyality (Treuepflicht): "They shall be independent of contractors and suppliers"
  • Duty of diligence (Sorgfaltspflicht): "They shall act responsibility towards the environment and the public"

Consultant: Delivers intellectual service, with an unknown output.

Work: Delivers a product whith a clear predefined outcome. 

Define a Project.

  • Clear defined starting- and endpoint
  • outcome is unknown and unique

Draw the swiss service model for a leading consultant and highlight the basic services according to SIA.

  • Strategic briefing
  • Plreliminary Studies
  • Project*
  • Invitation to tender (Ausschreibung)*
  • Implementation*
  • Operation

*Basic services

What are the differences between the Swiss and German Service model?

Swiss:

  • Division in "Phases"
  • Only a recommendation
  • non-compulory phases like "strategic breefing", "pleliminary studies", "Operation"

German:

  • Division in "Working Packages"
  • Every working package belongs to the basic service. -> leading consultant must do everything. 

Name the Subphases of "Strategic Planning" and its goals.

  • Definition of needs, solution strategies.

Goal: Determination of of needs, solution strategies

Name the Subphases of "Preliminary Studies" and its goals.

  • Project definition, feasibility study (Machbarkeitsstudie)
  • Selection procedures: Select the option which meets the requirements best.

Name the Subphases of "Project" and its goals.

  • Preliminary project: Concept and profitability optimized
  • Construction project: Project and cost optimized, defined
  • Permit-abtaining procedure:

Name the Subphases of "Intivation to bid / tender" and its goals.

  • Invitation, comparison of quotation, application for contract awarding