Which one of the following is NOT a technique/ tool of the Control Risks process?

Budget at Completion (BAC) ...

Which of the following is a task of the process 'Close Project or Phase'?

A schedule performance index (SPI) of 0.76 means:

If earned value (EV) = 350, actual cost (AC) = 400, planned value (PV) = 325, what is the
schedule variance (SV)?

An output of the Close Project or Phase process is the creation of:

Which processes are contained by the Closing Process Group?

Estimate at completion (EAC) is a periodic evaluation of: