Which of the following statements regarding this decision tree is correct?

 

As the impact is the same (1.000) for both airlines you can choose any of them.

You should choose Airline A because the EMV is less than the EMV of Airline B

You should choose Airline B because the EMV is 2.000 and this is more than the EMV of Airline A

It is better to choose Airline A because the ticket itself is cheaper.

Fenster schliessen

Which of the following activities doesn't occur during the Plan Procurements process?

Answering sellers' questions about the bid documents

Create Procurement Management Plan

Create Procurement Statement of Work (SOW)

Make‐or‐buy decision

Fenster schliessen
Lizenzierung: Keine Angabe

Which of the following risks is the biggest threat to the project?

4

1

2

3

Fenster schliessen

Which one of the following is NOT a response strategy for negative risks or threats?

Exploit

Avoid

Mitigate

Transfer

Fenster schliessen

The procurement statement of work, which is an output of the Plan Procurement Management
proces, is NOT based on...

Scope statement

WBS Dictionary

Stakeholder management plan

WBS

Fenster schliessen

A project manager is in the middle of creating a request for proposal (RFP). What part of the
procurement process is she in?

Plan Procurement

Administer Procurements

Make-or-Buy Analysis

Conduct Procurements

Fenster schliessen

f you ask the client to handle some of the work which type of risk response is this?

Avoid

Mitigate

Transfer

Accept

Fenster schliessen

With which type of contract is the seller MOST concerned about project costs?

Purchase order

Cost reimbursable contract

Time and material

Fixed price